S.L. 545.1 чл. 34Payment by instalments for the cost of an installationandHT contribution.

В силаОфициален текст

The cost of an installation and H.T. contribution to be carried out by the distribution system operator is to be paid under the following conditions:

(a) estimates below €2,329 to be paid in full on contract;

(b) estimates above €2,329 to he paid 50% on contract and

50% prior to energizing of extension, subject to a minimum deposit of €2,329.

История на изменения
  • Amended by L.N. 52 of 2010