S.L. 549.78 · Industrial Emissions (S.L. 549.78)
S.L. 549.78 Art. 8Conditions for gas turbines.
(1) Permits for gas turbines which have been granted a permit before the 07 January 2013, or the operators of which have submitted a permit before that date, provided that such plants are put into operation no later than 07 January 2014 shall include conditions related to emission limit values which shall not be higher than those in Schedule IX.
(2) Permits for other gas turbines outside the scope of sub-regulation (1) shall include conditions related to emission limit values, which shall not be higher than those in Schedule X.