S.L. 623.6 · Avoidance Of Damage To Third Party (S.L. 623.6)

S.L. 623.6 Art. 10Compliance with method statement or enforcement notice.

In forceOfficial text

(1) When the site technical officer is in doubt about how works are to proceed, he shall stop the works and request direction from the who would have prepared the method perit statement.

(2) The site technical officer shall ensure that the contractor is complying with all their obligations as provided for in these regulations. If the site technical officer notices any violation of these regulations, he shall immediately stop the works and notify the perit(i) in charge and the Building and Construction Authority.

(3) Upon being served with an enforcement notice issued by the Director, the site technical officer shall immediately communicate this notice to the contractor and the and see to it that this order is perit(i) complied with by ceasing the demolition, excavation and/or construction activity, as applicable.