S.L. 552.12 · Development Planning (Fees) (S.L. 552.12)
S.L. 552.12 Art. 20calculated contribution a dismissal in Planning Authority: (ii) and (iii) will always be retained to (iv) if (v) if (vi) if to 21. Where exceptional scale of the and other and regulate Structure Plan Schedule is to meet the and may also contribution to the 22. (a) (b) (c) 23. Where as the new writin
All Infrastructure Services Contributions shall be levied at rates with reference to the development proposed in the application and no shall be refundable except in the following cases:
(i) the permission applied for has been refused, unless it is terms of section 52(5) of the Environment and Development Act;
(ii) the application has been invalidly made;
(iii) the application is withdrawn before it is determined by the
Provided that in the cases mentioned in sub-paragraphs (i), abovementioned, 10% of the infrastructure services contributions cover administrative charges and are consequently not refundable;
it is made in respect of an application for a class of development for which such permission is not required by or under any provision of the Act or any regulations or orders made thereunder, and the application is returned by the Authority to the applicant; the application is one to which paragraph 19(a) relates, and the applicant subsequently provides the appropriate services at his own expense and the relevant Department has certified that the works have been carried out to its satisfaction, a refund equal to 15% of the infrastructure services contribution shall be paid; the application is one to which paragraph 19(b) relates, and the relevant Department has certified that the works have been carried out its satisfaction, a refund equal to 15% of the infrastructure services contribution shall be paid;
the Authority considers that in order to meet the extraordinary or demands which, in the opinion of the Authority, the nature, location or proposed development is likely to place on the infrastructure services services or facilities, as well as to secure the proper planning of the area the use of land in accordance with the policies and proposals in the and any subsidiary plan, the contribution earlier specified in this insufficient, the Authority shall determine the contribution to be levied cost of the services and facilities arising from the permission applied for, enter into agreement with the applicant to ensure the payment of the so determined and the proper carrying out of the development according permission of the Authority;
Applications for an Outline Development Permit with a site area of less than or equal to 1,000 square meters shall be submitted to the Authority together with the payment of a Development Permit Fee of €500. Applications for an Outline Development Permit with a site area of more than 1,000 square meters shall be submitted to the Authority together with the payment of a Development Permit Fee of €2,500. The development permit fees mentioned in paragraphs (a) and (b) shall not be refunded but shall be deducted from the Development Permit Fee due for the eventual full application; an application is submitted for new development on a site (described application for the purpose of this paragraph) and the applicant states in application for development of the same type had previously been submitted by the applicant on another site (described as the original site the purpose of this paragraph) in the vicinity of the new site and had been approved; and the infrastructure services contribution paid in relation to the application on the original site should be taken into account in the calculation of the Infrastructure Services Contribution due on the application for the new site; the original site shall be cancelled by the Authority and the services contribution shall be deemed not to have been paid on the The infrastructure services contribution paid on the original site shall account in the calculation of the infrastructure services contribution to relation to the new application;