S.L. 601.3 · Public Procurement Regulations (S.L. 601.3)

S.L. 601.3 Art. 122Accelerated process.

Van krachtOfficiële tekst

Where a state of urgency duly substantiated by the contracting authorities renders impracticable the time limits laid down in the previous regulation, they may fix:

(a) a time limit for the receipt of requests to participate which shall not be less than fifteen days from the date on which the contract notice was sent;

(b) a time limit for the receipt of tenders which shall not be less than ten days from the date on which the invitation to tender was sent.