S.L. 601.3 · Public Procurement Regulations (S.L. 601.3)
S.L. 601.3 ст. 177Obligations of contracting authorities.
(1) For the purposes of awarding contracts under a dynamic purchasing system, the authorities responsible for the tendering process shall:
(a) publish a call for competition making it clear that a dynamic purchasing system is involved;
(b) indicate in the procurement documents at least the nature and estimated quantity of the purchases envisaged, as well as all the necessary information concerning the dynamic purchasing system, including how the dynamic purchasing system operates, the electronic equipment used and the technical connection arrangements and specifications;
(c) indicate any division into categories of products, works or services and the characteristics defining them;
(d) offer unrestricted and full direct access, as long as the system is valid, to the procurement documents in conformity with regulation 49.
(2) The authorities responsible for the tendering process shall give any economic operator, throughout the entire period of validity of the dynamic purchasing system, the possibility of requesting to participate in the system under the conditions referred to in regulation 175.
(3) Contracting authorities shall finalise their assessment of the requests identified under sub-regulation (2) in accordance with the selection criteria within ten working days following their receipt.
(4) The deadline established in sub-regulation (3) may be prolonged to fifteen working days in individual cases where justified, in particular because of the need to examine additional documentation or to otherwise verify whether the selection criteria are met.
(5) Notwithstanding the provisions of sub-regulations (2), (3) and (4), as long as the invitation to tender for the first specific procurement under the dynamic purchasing system has not been sent, the authorities responsible for the tendering process may extend the evaluation period provided that no invitation to tender is issued during the extended evaluation period. The authorities responsible for the tendering process shall indicate in the procurement documents the length of the extended period that they intend to apply.
(6) The authorities responsible for the tendering process shall inform the economic operator concerned at the earliest possible opportunity of whether or not it has been admitted to the dynamic purchasing system.
(7) The authorities responsible for the tendering process shall invite all admitted participants to submit a tender for each specific procurement under the dynamic purchasing system, in accordance with regulation 50. Where the dynamic purchasing system has been divided into categories of works, products or services, the authorities responsible for the tendering process shall invite all participants having been admitted to the category corresponding to the specific procurement concerned to submit a tender.
(8) They shall award the contract to the tenderer that submitted the best tender on the basis of the award criteria set out in the contract notice for the dynamic purchasing system. Those criteria may, where appropriate, be formulated more precisely in the invitation to tender.