S.L. 499.12 Art. 71Data requirements.
PART IV
In addition to the safety and pollution prevention/control data referred to in regulation 70, the following information shall also be provided to the Authority by such operators:
(1) full general details of:
(a) equipment layout plans dealing with the most safety and environmentally hazardous operations that are or shall be undertaken at that marine terminal/facility;
(b) the routine pollution prevention/control procedures and equipment both within the terminal/facility and as required by the terminal/facility operator to be on board ships or bunker barges utilising his facilities;
(c) the operations manual;
(d) the operations checklists;
(e) all safety and pollution prevention/control training programmes provided to personnel;
(f) all prescribed emergency procedures;
(g) ship data records concerning incidents and turnaround reports;
(h) routine and exceptional manning schedules;
(i) plans of the general terminal/facility layouts;
(j) the terminal/facility regulations;
(k) descriptions of known problem areas at the terminal or facility;
(l) list of Marine maintenance work orders;
(m) preventive maintenance and inspection procedures;
(n) the means and procedures provided by the terminal or facility for effective communications between all concerned persons during a ship's transit to and from berths or moorings, at berths or moorings and during cargo handling/COW/tank cleaning and bunker operations;
(o) the organisation chart of the marine terminal/facility;
(2) with regard to facilities available for each berth, mooring or jetty full details of:
(a) the number of moorings, jetties or berths available;
(b) the maximum and minimum sizes of ships for which each mooring, berth, and jetty is designed;
(c) the maximum and minimum actual depths of water available at each mooring, berth or jetty;
(d) the cargo transfer systems provided at each mooring, berth or jetty;
(e) product types and volumes actually being handled at each mooring, berth or jetty and the product type and volumes for which each was designed to be capable of handling;
(f) the product slates for each mooring, berth or jetty;
(g) the general layout of each mooring, berth or jetty;
(h) the designed and actual environmental constraints for each mooring, berth or jetty, including wind and sea state;
(3) with regard to mooring layouts full details of:
(a) the maximum design mooring loads and permissible number of lines per hook, bollard or mooring;
(b) the design and actual physical constraints for each mooring, berth or jetty, including:
(i) maximum ship LOA and beam;
(ii) minimum and maximum freeboard;
(iii) deadweight displacement;
(iv) position of transfer manifold(s);
(v) angle, direction and approach velocity for berthing or mooring operations;
(c) damage reports for each mooring, berth or jetty;
(4) with regard to cargo transfer full details of:
(a) the environmental limits of equipment such as hard-arms, booms, etc;
(b) the operating envelopes for hard-arms, booms, etc. including the limits of drift and surge;
(c) the simultaneous cargo handling and/or ballast procedures and possibilities routinely conducted or available at each mooring, berth or jetty;
(d) the manifold connection criteria;
(e) the flow rates, temperature and pressures at which substances are routinely handled and the design limits of the transfer system in respect of such matters;
(f) cargo hose specifications;
(g) hose-testing and inspection criteria and records;
(h) hard-arm/hose operating instructions, including drift and surge detection and emergency release systems;
(i) over-pressure protection systems and inspection criteria;
(5) with regard to pollution prevention full details of:
(a) all historical incident reports;
(b) spill clean-up plans and equipment;
(c) emergency shut-down system details, such as remotely operated block valves, check valves, alarms and testing/inspection criteria;
(d) pollution prevention checklist;
(e) pollution control contingency plans for both operations conducted at the terminal/facility, its moorings, berths and jetties, by the operator or by third party bunker barges permitted by the operator to use such facilities for bunkering operations;
(6) with regard to safety, full details of:
(a) the berth, jetty and terminal/facility surveillance and security systems, procedures and practices;
(b) safety checklists;
(c) the means of egress from the berths or jetties of a terminal/facility (especially in case of an emergency);
(d) fire-fighting equipment, including the number and location of monitors, hydrants and portable extinguishers and the design flow rates and pressure for foam and water systems;
(e) life-saving and personnel protective equipment;
(f) contingency plans for effectively dealing with fire, safety incidents and emergencies at the moorings, berths or jetties at the terminal/facility or on board any third-party bunker barge permitted by the operator to use his terminal or facility.